Association Updates

WINTER 2021

2020 Annual Meeting: The Board of Directors would like to thank all Members who returned ballots for the Homeplace Annual Meeting since the Annual Meeting could not be held in person due to the CoVid-19 pandemic. A returned mail quorum was established that re-elected Kathleen Sullivan and Jennifer Britt each to an additional 3-year term […]

WINTER 2021 Read More »

SPRING 2016

Summer Pruning:  The pruning of all community bushes and shrubs was completed prior to Summer, earlier than anticipated, due to the excessive rain that promoted late Spring growth. Some pruning of bushes and shrubs may appear to be more severe than others so they no longer rest against or attempt to climb up, on, into, or

SPRING 2016 Read More »

WINTER 2016

Winter 2016: Masonry & Concrete:  The milder Winter temperatures provided the opportunity for the few remaining front brick step and stoop replacements to resume earlier than planned on Saddlegate Court and Autumncrest Drive. When the brick masonry has been completed concrete repairs and replacements will be scheduled and occur next. The progression of this Capital Improvement

WINTER 2016 Read More »

FALL 2015

Front Railings:  After the front railing project was temporarily placed on hold to obtain a new masonry vendor, both have resumed. The front railing project has reached the finish line with all front railings on all townhomes completed. Railings have begun to be installed in the Common Area where more than three steps exist. This five-year

FALL 2015 Read More »

SUMMER 2015

Front Railings:  The front railing project in addition to the front brick step and stoop replacements resumed during the Spring; however, was temporarily placed on hold to obtain a new masonry vendor. Except for a remaining few, all front railings have been addressed and completed on all townhomes while a few masonry step and stoop work

SUMMER 2015 Read More »

SPRING 2015

Front Railings:  The front railing project in addition to the few remaining front brick step and stoop replacements has resumed now that warmer temperatures have returned. With the project now 90% complete it is expected to be finished this year. The progression of this five-year capital improvement project will continue to be dependent on weather conditions,

SPRING 2015 Read More »

WINTER 2015

Pine Needles:  Application of pine needles throughout the Common Areas and around all townhomes was completed the end of January. Please submit a Work Order for any area that needs to be addressed or may have been overlooked. Entrances:  The island at the Autumncrest entrance will be redesigned in March, or some time thereafter, when warmer Spring

WINTER 2015 Read More »

FALL 2014

Front Railings:  The front railing project is almost complete with Saddlegate completely finished. The budget for masonry and front railing replacements for the year has been completely utilized, will resume, and be completed next year. The progression of the project continues to be dependent on weather conditions, and primarily, as finances allow. Front Doors:  Painting of all

FALL 2014 Read More »

SUMMER 2014

Landscaping:  Pruning of shrubs throughout the community was completed just as the Summer season began. Please submit a Resident Work Order for any shrubs and foliage that may need additional pruning on an individual basis. Homeowners and residents may not put down mulch with personal plantings due to its nature for termite attraction and breeding. Personal plantings are

SUMMER 2014 Read More »

SPRING 2014

Landscaping:  Some landscaping improvements continue removing more of the old juniper bushes and cleaning up natural areas that have become overgrown. As a reminder, now that the warmer temperatures have arrived, homeowners and residents may not put down mulch with personal plantings due to its nature for termite attraction and breeding. Personal plantings are limited to the footprint

SPRING 2014 Read More »